Home/Projects/Macro tower antenna relocation & 5G upgrade

Macro tower antenna relocation & 5G upgrade

Macro tower · California · Antenna & line work

Tower climb — antenna installation

Scope of work

  • Relocate (3) Ericsson AIR 6449 antennas at position 2, all sectors
  • Install (3) Ericsson AIR 6419 at proposed RAD center
  • Install (3) SitePro1 P30120 mast pipes with SCX45-K crossover plates
  • Reinforce horizontal members of T-arms
  • Install (1) 6AWG DC trunk to final ground configuration

How it went

A permitted 5G capacity upgrade on an active macro site: existing massive-MIMO antennas moved down to make room for new mid-band units at the proposed RAD center, with mounts and T-arms reinforced to carry the added load. The site stayed on air throughout — work was sequenced sector by sector to keep coverage up.